Progress Report November 2024

Produced by Paul Krzywicki, Senior Project Manager

WORK COMPLETED:

  • Level 4 exterior walls framed
  • PMT grounding completed
  • Window testing completed

UPCOMING WORK:

  • Truss delivery November 12th
  • Exterior wall membrane continues
  • Window prep continues
  • Cladding mock-up